King Kong Levee: Two Miles Done, Two To Go
Compared to the myriad mini-levees planned around the Bay in 2025, the South Bay’s growing shoreline levee stands out for its sheer scale and engineering.
This is no mere mound of dirt, like the 19th century earthworks still keeping the Bay out of pastures and local salt ponds, nor an experiment in how to use wastewater to irrigate new gray-green levees and filter out nutrients while protecting sewage treatment plants from sea level rise.
These two miles of 15-foot-tall, 16-foot-wide-at-the-top levee are of the more traditional Army Corps, FEMA-approved style: a major, multi-benefit flood control project designed to protect the oft-water-logged town of Alviso and parts of San Jose. This September marked completion of Phase 1 after 20 years in planning, development, and construction. The entire project, which will stretch from Alviso Slough to Coyote Creek, is expected to be completed by 2035 (provided additional funding is forthcoming).
Richard Santos grew up in the tiny fishing town of Alviso and remembers the floods in the 1960s, ’80s, and 1995. “It wasn’t just the water, but the damage and fear they brought. This project is more than infrastructure; it’s an important step toward peace of mind, safety, and confidence for our community,” says the Valley Water board director.
“As extreme weather and climate change-related emergencies increase in frequency, I am glad to see these life-saving protections for San Jose residents completed,” says Rep. Zoe Lofgren (CA-18).
To date, the $545 million project has required complex collaborations among local jurisdictions and partners (Valley Water, the Army Corps of Engineers, the California Coastal Conservancy, the Don Edwards National Wildlife Refuge, the city of San Jose, a railroad, the local parks district, and more). Eventually, the project will also enable the restoration of almost 3,000 acres of tidal wetlands on former salt ponds and completion of the Bay Trail through the area.
More importantly, it offers a tangible on-the-ground reminder of the scale of project necessary in the future as the region looks to protect airports, urban waterfronts, bridge touch-downs, and shoreline freeways from the steady rise of the Bay due to global warming.
“No project on the San Francisco Bay shoreline is easy,” says the Conservancy’s Amy Hutzel. “It’s always a complicated mix of jurisdictions and landowners and utilities, infrastructure and communities, all with lots of different needs. The Shoreline Project, I think, is a really great model of what we can do here.”
Next steps include constructing and revegetatating an ecotone along the levee, which will provide habitat for wildlife, and completing the remaining two miles of levee.
Other Recent Posts
How Can I Get Clean, Green, Climate-Forward Job Training in the Bay Area?
Looking for a hands-on job working outdoors that actually pays? Here’s a list of training programs.
Santa Rosa Residents Rethink Trees
The heat-burdened Roseland neighborhood is learning how to monitor temperatures and developing an action plan focused on tree shade.
How to Make Conservation a Career
California nonprofits are developing paid apprenticeships to prepare workers for the growing ecological restoration economy.
Raft of Resilience Initiatives Keeps Tahoe Blue
Beach robots, boat inspections, forest thinning, and wetland restoration are among the projects helping the lake confront environmental threats.
Weathering the Present While Training for the Future
A stewardship immersion experience from the School for Inclement Weather and Weaving Earth combines ecological knowledge and spiritual connection.
Feds Meddling With Protections For California Coast
NOAA is reviewing California’s Coastal Management Program in a renewed push for offshore oil and gas drilling.
New Study Shows Rain Gardens Filter Chemicals Out of Stormwater
Scientists found rain gardens dramatically reduce toxic chemicals in stormwater while providing biodiversity and cooling.
MORE
- Delivering Tunnel Muck to South Bay Marshes, August 2024
- A South Bay Levee Breaks Ground, April 2022